EU funding instrument "Connecting Europe Facility" (CEF)
Actions co-financed by EU funding instrument "Connecting Europe Facility" (CEF)
The EU funding instrument "Connecting Europe Facility" (CEF) is co-financing the following actions with funding estimated at 188.3 million euros:
Mediterranean Corridor.Valencia - Camp de Tarragona section.Adaptation to UIC gauge.
- Estimated investment excluding VAT (million EUR):
252.1 - CEF funding (million EUR):
84.2
Mediterranean Corridor. Valencia - Sagunto - Castellón section. Implementation of UIC gauge
-
Project 2019-ES-TM-0235-W
- Estimated investment excluding VAT (million EUR):
103.8 - CEF funding (million EUR):
41.5
Atlantic Corridor.Vitoria - Bilbao - San Sebastián - French border line.Elorrio – Atxondo – Abadiño section.Track-bed
- Estimated investment excluding VAT (million EUR):
52.7 - CEF funding (million EUR):
10.5
Atlantic Corridor and Mediterranean Corridor.ERTMS migration 2.3.0.d Phase II.
- Estimated investment excluding VAT (million EUR):
7.5 - CEF funding (million EUR):
3.8
Atlantic Corridor.Valladolid - Venta de Baños and Venta de Baños - Burgos line.Implementation of ERTMS
- Estimated investment excluding VAT (million EUR):
15.6 - CEF funding (million EUR):
7.8
Atlantic Corridor.Chamartín – Torrejón section.Superstructure and environmental protection.
- Estimated investment excluding VAT (million EUR):
33.0 - CEF funding (million EUR):
9.9
Atlantic Corridor.Bergara - San Sebastián - Bayonne section.Studies and works. (*)
(*) Investment and funding for the Spanish section
- Estimated investment excluding VAT (million EUR):
57.4 - CEF funding (million EUR):
22.9
Corredor Atlántico. Autopista Ferroviaria Atlántica. Intercambio modal de todos los tipos semi-trailers
- Inversión estimada IVA excluido (millones de euros)
0.5 M€ - Ayuda CEF (millones de euros)
0,2 M€
Atlantic Corridor.Madrid Urban Hub.Atocha station railway complex.Studies
- Estimated investment excluding VAT (million EUR):
2.2 - CEF funding (million EUR):
1.1
Atlantic Corridor.Sines/Lisbon-Madrid high-speed line.Madrid Urban Hub.Chamartín station.Access to new connections with the underground network and high-speed connection with Barajas airport.Studies
- Estimated investment excluding VAT (million EUR):
0.2 - CEF funding (million EUR):
0.1
Atlantic Corridor.Sines/Lisbon-Madrid high-speed line.Madrid Urban Hub.Study of the Atocha station railway complex (Phase III)
- Estimated investment excluding VAT (million EUR):
11.4 - CEF funding (million EUR):
5.7
Atlantic Corridor.Remodelling of the Madrid - Chamartín railway complex for its adaptation to high-speed services
- Estimated investment excluding VAT (million EUR):
1.6 - CEF funding (million EUR):
0.8
Improvements to station accessibility.
- Estimated investment excluding VAT (million EUR):
0.2 - CEF funding (million EUR):
0.1
Total CEF investment and fundingHighlighted paragraph
- Estimated investment excluding VAT (million EUR):
537.6 - CEF funding (million EUR):
188.3
(Data as of 31 December 2020)