Barcelona Sants transformation project

Works plan to promote and improve infrastructure in the Catalan railway network

Title
  • A project for a station that will be a benchmark for future mobility.
  • Result of a participatory process developed over the last year with local organizations, neighborhood associations and businesses.
  • It will be developed progressively in phases culminating, after a ten or so actions that will end, in the first stage, in mid-2026
Integrated into the environment and people-oriented
  • Integration into a new urban model, eliminating the traffic circle effect and facilitating the permeability of pedestrian connections.
  • It limits vehicular traffic to Viriat, in addition to eliminating vehicles on the north side of Passeig de Sant Antoni, which will be replaced by a public space.
  • It will have a large children's play area and the original water fountains in Països Catalans square will be restored.
Multimodality and sustainable mobility
  • A new Metro concourse will be created to connect with Rodalies and Alta Velocidad.
  • The so-called "mountain side" will be configured as a space for active and last-mile mobility, from bicycles to scooters and wide pedestrian areas.
  • The mountain side will also connect with a new bike lane.
Sustainability
  • It will contribute to reducing CO2 emissions and promote a zero-waste environment.
  • It will provide natural lighting and ventilation.
  • Natural materials with a low carbon footprint, such as granite, wood and metal, will be used in the construction.

 

Multimedia Galleries: Projects in Catalonia

  1. 27 de octubre de 2025. Plaza Països sustitución de salidas de emergencia.
  2. 22 de octubre de 2025. Sustitución de neoprenos.
  3. 22 de octubre de 2025. Sustitución de neoprenos.
  4. 22 de octubre de 2025. Sustitución de neoprenos.
  5. 22 de octubre de 2025. Sustitución de neoprenos.
  6. 14 de octubre de 2025. Fase 1 construcción del nuevo depósito de prevención contra incendios
  7. 23 de septiembre de 2025. Plaça Països demoliciones.
  8. 18 de septiembre de 2025. Plaça Països Impermeabilización.
  9. 6 de agosto de 2025. Fase 1 pruebas de estanqueidad cubierta.
  10. 16 de julio de 2025. Demolición entornos montaña.
  11. 1 de julio de 2025. Plaça Països pruebas estanqueidad.
  12. 19 de junio de 2025. Fase 1 demolición de locales comerciales.
  13. 17 de junio de 2025. Pruebas de estanqueidad entornos mar.
  14. 17 de junio de 2025. Construcción kiss and train en los entornos del mar.
  15. 4 de junio de 2025. Impermeabilización entornos montaña.
  16. Barcelona Sants. Infografía zona de embarque Alta Velocidad
  17. Barcelona Sants. Infografía Área de Països Catalans
  18. Barcelona Sants. Infografía exterior lado Països Catalans
  19. Barcelona Sants. Infografía alzado zona Espanya Industrial
  20. Barcelona Sants. Infografía alzado lado J. Peiró
  21. Barcelona Sants. Infografía alzado Lado Viriat
  22. Barcelona Sants. Infografía interior eje transversal
  23. Barcelona Sants. Infografía interior eje longitudinal
  24. Barcelona Sants. Infografía interior zona Rodalies lado Plaza Peiró
  25. Barcelona Sants. Infografía que recoge el manto verde que cubrirá el edificio
Skip carousel
27 de octubre de 2025. Plaza Països sustitución de salidas de emergencia.
27 de octubre de 2025. Plaza Països sustitución de salidas de emergencia.
22 de octubre de 2025. Sustitución de neoprenos.
22 de octubre de 2025. Sustitución de neoprenos.
22 de octubre de 2025. Sustitución de neoprenos.
22 de octubre de 2025. Sustitución de neoprenos.
22 de octubre de 2025. Sustitución de neoprenos.
22 de octubre de 2025. Sustitución de neoprenos.
22 de octubre de 2025. Sustitución de neoprenos.
22 de octubre de 2025. Sustitución de neoprenos.
14 de octubre de 2025. Fase 1 construcción del nuevo depósito de prevención contra incendios
14 de octubre de 2025. Fase 1 construcción del nuevo depósito de prevención contra incendios
23 de septiembre de 2025. Plaça Països demoliciones.
23 de septiembre de 2025. Plaça Països demoliciones.
18 de septiembre de 2025. Plaça Països Impermeabilización.
18 de septiembre de 2025. Plaça Països Impermeabilización.
6 de agosto de 2025. Fase 1 pruebas de estanqueidad cubierta.
6 de agosto de 2025. Fase 1 pruebas de estanqueidad cubierta.
16 de julio de 2025. Demolición entornos montaña.
16 de julio de 2025. Demolición entornos montaña.
1 de julio de 2025. Plaça Països pruebas estanqueidad.
1 de julio de 2025. Plaça Països pruebas estanqueidad.
19 de junio de 2025. Fase 1 demolición de locales comerciales.
19 de junio de 2025. Fase 1 demolición de locales comerciales.
17 de junio de 2025. Pruebas de estanqueidad entornos mar.
17 de junio de 2025. Pruebas de estanqueidad entornos mar.
17 de junio de 2025. Construcción kiss and train en los entornos del mar.
17 de junio de 2025. Construcción kiss and train en los entornos del mar.
4 de junio de 2025. Impermeabilización entornos montaña.
4 de junio de 2025. Impermeabilización entornos montaña.
Barcelona Sants. Infografía zona de embarque Alta Velocidad
Barcelona Sants. Infografía zona de embarque Alta Velocidad
Barcelona Sants. Infografía Área de Països Catalans
Barcelona Sants. Infografía Área de Països Catalans
Barcelona Sants. Infografía exterior lado Països Catalans
Barcelona Sants. Infografía exterior lado Països Catalans
Barcelona Sants. Infografía alzado zona Espanya Industrial
Barcelona Sants. Infografía alzado zona Espanya Industrial
Barcelona Sants. Infografía alzado lado J. Peiró
Barcelona Sants. Infografía alzado lado J. Peiró
Barcelona Sants. Infografía alzado Lado Viriat
Barcelona Sants. Infografía alzado Lado Viriat
Barcelona Sants. Infografía interior eje transversal
Barcelona Sants. Infografía interior eje transversal
Barcelona Sants. Infografía interior eje longitudinal
Barcelona Sants. Infografía interior eje longitudinal
Barcelona Sants. Infografía interior zona Rodalies lado Plaza Peiró
Barcelona Sants. Infografía interior zona Rodalies lado Plaza Peiró
Barcelona Sants. Infografía que recoge el manto verde que cubrirá el edificio
Barcelona Sants. Infografía que recoge el manto verde que cubrirá el edificio

Download

27 de octubre de 2025. Plaza Països sustitución de salidas de emergencia.
22 de octubre de 2025. Sustitución de neoprenos.
22 de octubre de 2025. Sustitución de neoprenos.
22 de octubre de 2025. Sustitución de neoprenos.
22 de octubre de 2025. Sustitución de neoprenos.
14 de octubre de 2025. Fase 1 construcción del nuevo depósito de prevención contra incendios
23 de septiembre de 2025. Plaça Països demoliciones.
18 de septiembre de 2025. Plaça Països Impermeabilización.
6 de agosto de 2025. Fase 1 pruebas de estanqueidad cubierta.
16 de julio de 2025. Demolición entornos montaña.
1 de julio de 2025. Plaça Països pruebas estanqueidad.
19 de junio de 2025. Fase 1 demolición de locales comerciales.
17 de junio de 2025. Pruebas de estanqueidad entornos mar.
17 de junio de 2025. Construcción kiss and train en los entornos del mar.
4 de junio de 2025. Impermeabilización entornos montaña.
Barcelona Sants. Infografía zona de embarque Alta Velocidad
Barcelona Sants. Infografía Área de Països Catalans
Barcelona Sants. Infografía exterior lado Països Catalans
Barcelona Sants. Infografía alzado zona Espanya Industrial
Barcelona Sants. Infografía alzado lado J. Peiró
Barcelona Sants. Infografía alzado Lado Viriat
Barcelona Sants. Infografía interior eje transversal
Barcelona Sants. Infografía interior eje longitudinal
Barcelona Sants. Infografía interior zona Rodalies lado Plaza Peiró
Barcelona Sants. Infografía que recoge el manto verde que cubrirá el edificio
Visit other galleries that may be of interest, related to the different thematic sections.
Skip carousel
Related press releases
Barcelona Estació de França luce la renovada cubierta de su histórica marquesina, referente de la Ciudad Condal
Adif presenta los avances y planificación de los proyectos de protecciones acústicas en la provincia de Tarragona
Adif y el Ayuntamiento de Reus firman un protocolo para mejorar la integración del ferrocarril en la ciudad
Adif pone en servicio las nuevas instalaciones de la estación de Fornells de la Selva (Girona)
Adif inicia las pruebas con un tren de ancho internacional en el nudo de Castellbisbal del Corredor Mediterráneo
Adif y Adif AV convocan a cerca de 17.000 candidatos para las pruebas selectivas de sus últimas convocatorias de empleo
Adif AV adjudica por 6,32 millones de euros actuaciones de refuerzo y mejora de dos viaductos de la LAV Madrid-Barcelona
Adif adjudica por 41,3 M€ trabajos para garantizar el tráfico de trenes durante las obras de integración del ...
Adif finaliza la primera fase de las obras de mejora integral de la estación de Montcada-Bifurcació
Adif adjudica por 7 M€ la construcción del nuevo edificio de viajeros de la estación de Montcada-Bifurcació
Adif adjudica la instalación de sistemas de información al viajero en las estaciones de las terminales T1 y T2
Adif AV destina 3,7 M€ a las instalaciones del acceso a la Zona de Tratamiento Técnico de Trenes de la Sagrera
Adif invierte 6,2 M€ en renovar la vía de un tramo de 31km de la línea convencional Zaragoza-Lleida-Tarragona
Adif licita por más de 23 M€ el tratamiento integral del túnel ferroviario en Rubí
Adif licita la gestión de 15.120 m2 en la terminal de transporte de mercancías de Pla de Vilanoveta (Lleida)
Adif licita por 11,8M€ las obras de dos pasos inferiores que suprimirán el paso a nivel de Flaçà (Girona)
Adif AV y el BEI firman un préstamo de 115 millones de euros para modernizar y ampliar la estación de Barcelona Sants
Adif adjudica por 1,4 millones de euros las obras para instalar nuevos cerramientos en la línea ferroviaria en el Vallès
Adif adjudica por 2,7M€ la instalación de nuevos cerramientos de seguridad en la línea ferroviaria en el Maresme
Adif licita por 3,7M€ la renovación y mejora de 7 pasos a nivel en las provincias de Huesca, Lleida, Barcelona y ...